Governor's Task Force on Contracting Reform
Project Plan and Timeline
|
Jul 16 |
· Planning meeting with committee Co-chairs, Commissioner Fleming and Senator Don DeFronzo (Fri, Jul 16, 10:00 am)
· Approval of approach and timeline
· Committee and workgroup membership
· Draft letter(s) to committee members |
|
Jul 19-23 |
· DPW contacts committee members/ send agenda/ prep for Jul 26
· DPW prepares draft guidelines package for (7) workgroups |
|
Jul 26-30 |
· First committee meeting (Mon, Jul 26, 9:30 am, Rm 1 E, LOB)
· Approach and timeline
· Designation of work group chairs, members, and users
1. Leasing: DPW
2. Construction procedures: DOT and DPW
3. Construction investigation, etc: Chief State’s Attorney
4. Personal Services: OPM
5. Property Management: DPW
6. Procurement: DAS
7. Ethics and Integrity: Governor’s Special Counsel
· Sen. DeFronzo and Comm. Fleming convene workgroup chairs to review charge/desired format for reports/timeline (Wed, Jul 28, 10:30am and Thur. July 29, 9:30 am, Room 532, SOB)
|
|
Aug 2-6 |
· Public Hearing (Mon, Aug 2, 10:00 am, LOB)
· Workgroups convene first meeting: user agencies presentations / schedule follow-up meetings/ designate responsibilities |
|
Aug 9-13 |
· Workgroups draft recommendations |
|
Aug 16-20 |
· Workgroup preliminary reports due to committee Co-chairs for review (Mon, Aug 16) |
|
Aug 23-27 |
· Reading/review of reports by committee members (Aug 16-24)
· Possible committee meeting to digest/discuss reports (Aug 19) CANCELLED
· Second committee meeting; briefing by workgroup representatives, feedback from committee, charge for any revisions (Wed, Aug 25, LOB )
· Revisions submitted to committee Co-chairs (by Aug 27) |
|
Aug 30-31 |
· Committee synthesizes recommendations and prepares final report (Aug 28-31)
· Possible committee meeting to review final report (Aug 31) CANCELLED
|
|
Sep 1 |
· Final report submitted to Governor Rell and committee members
|