ConnDOT: Project No. 167-108
Project Pages

Project No. 167-108


{South Portal}

Elevation View of South Portal

 

Municipalities: Town of Woodbridge, Town of Hamden, City of New Haven

 

Project Location: Heroes Tunnel (Bridge No. 00773)  Route 15 through West Rock Ridge


Project Map:  Click to view location map and anticipated project limits 


Project Description:

The Heroes Tunnel, also known as Bridge No. 00773, consists of twin 1,200 foot long horseshoe-shaped tunnels, carrying two lanes of Route 15 (Wilbur Cross Parkway) traffic in each direction through the West Rock Ridge.  The Heroes Tunnel carries approximately 71,000 vehicles daily and is a vital scenic connector between New York and Hartford, as well as an alternate expressway route to Interstate 95 and 91.  Structural, geometric, and drainage deficiencies have been identified within the Heroes Tunnel.  The general deterioration necessitates either rehabilitation or replacement.  In addition to the deteriorating condition of the tunnel, other characteristics are substandard such as the electrical and mechanical utilities, all of which would be upgraded or improved through this project. 


PUBLIC SCOPING MEETINGClick to view the Public Scoping Meeting Presentation

 

A Public Scoping Meeting for this project was held at the Woodbridge Senior Center at 7:00 p.m. on Thursday September 22, 2016.  Additional written comments from the public will be accepted until the close of business on Friday, October 7, 2016 for this meeting. However, general comments or questions regarding the project can be submitted at any time. 


Contact:     Mr. David A. Cutler, P.E. 

                  Transportation Supervising Engineer

                  Connecticut Department of Transportation

                  2800 Berlin Turnpike, Newington, CT 06131

Phone:       860-594-3210

E-Mail:       David.Cutler@ct.gov


PROJECT DOCUMENTS:





Content Last Modified on 10/13/2016 9:27:55 AM