ConnDOT: I-84 SPMT - Home
I-84 SPMT Project

 
 
{I-84 ABC Bridge}
 
Rehabilitation of Bridge Numbers 01235 and 01236,
Interstate 84 over Marion Avenue in Southington

DOT Project No. 0131-0194/195

 
 
{I-84 Ribbon Cutting}
 
Summary of Traffic Management Results
 

The east and westbound structures were replaced during the weekend of June 27-30, 2014.  The eastbound direction of Interstate 84 was fully open to all lanes of traffic at 4:40 p.m. and the westbound direction was opened at 8:15 p.m.

 

Gov. Malloy: Video Documents Creative Approach to Achieve Early Completion of CTDOT I-84 Bridge Replacement Project in Southington

 

The time lapse video that was provided by EarthCam, Inc. and also a time-lapse video produced by the Connecticut Department of Transportation is available for viewing at the following links: 

I-84 Southington Bridge Replacement ConnDOT Time Lapse

I-84 Southington Bridge Replacement Earthcam Time Lapse

 

{wmp} Windows Media Player©

PROJECT STATUS

The structures have been replaced utilizing Accelerated Bridge Construction (ABC) to minimize the impact to the traveling public. All lanes are open to traffic.

The project is still ongoing but the work isn't impacting traffic. There is still the demolition of the  existing bridges and any debris in the area to be removed.

 
INFORMATIONAL LINKS
 
 
Overall Project
      
Project Photos
{Updated}