ConnDOT: Stage 3 Demolition of the Existing Superstructure of the I-95 Bridge over the West River in New Haven and West Haven is scheduled to begin on Monday Night, September 12, 2016
2016

CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
 
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7546
 
FOR RELEASE: August 29, 2016
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot 

Stage 3 Demolition of the Existing Superstructure of the I-95 Bridge over the West River in New Haven and West Haven is scheduled to begin on Monday Night, September 12, 2016

  
The Connecticut Department of Transportation is announcing that the Stage 3 demolition of the superstructure of the existing I-95 bridge over the West River is scheduled to begin on Monday night, September 12, 2016. Lane closures on both I-95 northbound and southbound will be required to complete the superstructure demolition.

Lane Closure Information

Traffic on I-95 between Exits 42 and 46 will be reduced to one lane in each direction for approximately three weeks as follows:

 Beginning on 9/12: 10:00 p.m. to 6:00 a.m., Monday through Thursday nights
 Beginning on 9/18: Saturday night at midnight to 8:00 a.m. Sunday morning

Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions.  Motorists are advised to maintain a safe speed when driving in this vicinity.


Content Last Modified on 8/29/2016 3:08:53 PM