ConnDOT: Closure Schedule of East River Drive Ramp for Bridge Joint Repair on Route 15 Southbound over the Connecticut River the Charter Oak Bridge in East Hartford
2014

CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
 
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7546
 
FOR RELEASE: November 14, 2014
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot 

Closure Schedule of East River Drive Ramp for Bridge Joint Repair on Route 15 Southbound over the Connecticut River the Charter Oak Bridge in East Hartford

 

      The Connecticut Department of Transportation is announcing that the East River Drive On Ramp is scheduled to be closed between the hours of 4 pm and 7 am from Monday, November 17 through Wednesday, November 19 to work on the approach to Charter Oak Bridge, Route 15 southbound over the Connecticut River. 

 

      DOT Project No. 0063-0706, was awarded to Rotha Construction of Avon, CT and is being administered by the Office of Construction, District 1 Rocky Hill.  The work is scheduled to be completed in December 2014.

 

Lane Closure Information

Daytime operations

Tuesday and Wednesday between 11 AM and 2 PM  

All other times during the day only shoulder closures allowed

 

Nighttime operations

Monday and Tuesday - 7 PM to 7 AM following day

Wednesday and Thursday 8 PM to 7 AM following day

Friday - 9 PM to 9 AM Saturday

Saturday 8 PM to 11 AM Sunday

Sunday - 9 PM to 7 AM Monday

 

East River Drive On Ramp Detour

Signs will be in place to detour traffic to I-91 South and Route 5/15 south via the Silver Lane entrance ramp

 

Special Note- No work will be performed during the Thanksgiving holiday from Wednesday November 26 through 8 pm Monday, December 2, 2014



Content Last Modified on 11/14/2014 10:12:56 AM