Connecticut Siting Council
Apr 18, 2013

Energy/telecommunications meeting in New Britain

DATE:     April 11, 2013

TO:           Council Members

FROM:    Robert Stein, Chairman

RE:           Connecticut Siting Council Energy/Telecommunications Meeting


A meeting of the Connecticut Siting Council (energy/telecommunications) will be held on April 18, 2013, at 1:00 p.m. in Hearing Room Two, Ten Franklin Square, New Britain, Connecticut.

AGENDA

  1. Minutes of April 4, 2013.

  2. DOCKET NO. 190 Meriden Gas Turbines, LLC Certificate of Environmental Compatibility and Public Need for the Meriden Power Project located in the City of Meriden and the Town of Berlin, Connecticut. Petition of the City of Meriden to Reopen and Modify Decision and Order Due to Changed Conditions. City of Meriden Request for Party Status.

  3. DOCKET NO. 265A - Dominion Nuclear Connecticut, Inc. Application to Amend and Modify the Certificate of Environmental Compatibility and Public Need for the existing independent spent fuel storage installation at Millstone Power Station, Rope Ferry Road, Waterford, Connecticut pursuant to Connecticut General Statutes 4-181a(b) for the limited purpose of determining if changed conditions related to the existing independent spent fuel storage installation justify a modification of the Decision and Order. Draft Findings of Fact.
  4. DOCKET NO. 401 - T-Mobile Northeast LLC, Certificate of Environmental Compatibility and Public Need for the Construction, Maintenance and Operation of a Telecommunications Facility at 208 Valley Road, New Canaan, Connecticut. Request for Extension.

  1. DOCKET NO. 412 - SBA Towers III and New Cingular Wireless PCS, LLC Certificate of Environmental Compatibility and Public Need for the construction, maintenance and management of a telecommunications facility located at Wewaka Brook Road, Bridgewater, Connecticut. Request for Extension.
  2. DOCKET NO. 435 - The Connecticut Light & Power Company Application for a Certificate of Environmental Compatibility and Public Need for the Stamford Reliability Cable Project, which consists of construction, maintenance, and operation of a new 115-kV underground transmission circuit extending approximately 1.5 miles between Glenbrook and South End Substations, Stamford, Connecticut and related substation improvements. Motion to Reopen Evidentiary Record.

  1. PETITION NO. 1056 - GRE 314 East Lyme, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction and operation of a 5.0 MW Solar Photovoltaic Renewable Energy Generating Project located on Grassy Hill Road and Walnut Hill Road, East Lyme, Connecticut. Draft Findings of Fact.

  1. PETITION NO. 1058 - The Connecticut Light and Power Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed 1990 line structure replacement project consisting of modifications of two sections of an existing 115-kV transmission line from Stevenson Substation to Frost Bridge Substation and from Baldwin Junction to Baldwin Substation traversing the municipalities of Monroe, Oxford, Middlebury, Waterbury and Watertown, Connecticut. Set Date for Decision.

  1. Emergency Disaster Recovery Deployment - EM-CING-085-121218 - New Cingular Wireless PCS, LLC notice of intent to install a temporary cellular telephone facility for use at town own property located at 375 Fan Hill Road, Monroe, Connecticut. Request for Extension.

  1. Wind Regulations.

  1. Administrative Matters.

Regular Items

> Upcoming Calendar Events:

Thursday, April 25, 2013, beginning at 2:00 p.m. field review and public hearing for

Docket No. 434 (Verizon-West Hartford) at the West Hartford Town Hall, Room 314,

50 South Main Street, West Hartford, Connecticut.

Tuesday, April 30, 2013, beginning at 2:00 p.m. field review and public hearing 3:30 p.m.

for Docket No. 409A (AT&T-Falls Village) at the Lee H. Kellogg School, All Purpose Room,

47 Main Street, Falls Village, Connecticut.

Thursday, May 2, 2013, beginning at 1:00 p.m. energy/telecommunications meeting,

in Hearing Room Two, Ten Franklin Square, New Britain, Connecticut.

1 PM