Connecticut Siting Council
Jun 20, 2013

Docket No. 435 (CL&P) Evidentiary Hearing in New Britain

DATE:             April 19, 2013

 

TO:                  Parties & Intervenors

 

FROM:             Linda Roberts, Executive Director

 

RE:                  DOCKET NO. 435 - The Connecticut Light & Power Company Application for a Certificate of Environmental Compatibility and Public Need for the Stamford Reliability Cable Project, which consists of construction, maintenance, and operation of a new 115-kV underground transmission circuit extending approximately 1.5 miles between Glenbrook and South End Substations, Stamford, Connecticut and related substation improvements.

 

 

During a meeting of the Connecticut Siting Council (Council) held on April 18, 2013, the Council, on its own motion, voted to reopen the evidentiary record for the above-referenced proceeding.

 

An additional public hearing has been scheduled for Thursday, June 20, 2013 in Hearing Room Two, 10 Franklin Square, New Britain commencing at 1 PM.

 

Parties and intervenors are requested to file additional interrogatories on or before Thursday, May 20, 2013. Additional pre-filed testimony and responses to interrogatories are requested to be filed on or before Thursday, June 13, 2013.

1 PM

Go Back