Connecticut Siting Council
Oct 26, 2017

Energy/telecommunications meeting in New Britain

DATE:    October 19, 2017

TO:        Council Members

FROM:    Robert Stein, Chairman

RE:        Connecticut Siting Council Energy/Telecommunications Meeting


An Energy/Telecommunications meeting of the Connecticut Siting Council will be held on October 26, 2017, at 1:00 p.m. in Hearing Room Two, Ten Franklin Square, New Britain, Connecticut.

AGENDA

  1. Minutes of September 28, 2017

  2. DOCKET NO. 461A - Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 115-kilovolt (kV) bulk substation located at 290 Railroad Avenue, Greenwich, Connecticut, and two 115-kV underground transmission circuits extending approximately 2.3 miles between the proposed substation and the existing Cos Cob Substation, Greenwich, Connecticut, and related substation improvements. Draft Findings of Fact.

  3. DOCKET NO. 478 - Eco-Site, Inc. and T-Mobile Northeast, LLC application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located at 63 Woodland Street, Glastonbury, Connecticut. Completeness Review, Schedule, Deposition of Transcript, Request for Party/Intervenor Status.

  4. PETITION NO. 1313 - DWW Solar II, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of a 26.4 megawatt AC solar photovoltaic electric generating facility on approximately 289 acres comprised of 5 separate and abutting privately-owned parcels located generally west of Hopmeadow Street (US 202/CT 10), north and south of Hoskins Road, and north and east of County Road and associated electrical interconnection to Eversource Energy’s North Simsbury Substation west of Hopmeadow Street in Simsbury, Connecticut. Flammini, et al. Request to Withdraw Testimony and Exhibits of George Logan. Flammini, et al. Request for Relief from Order to Compel Interrogatory Responses.

  5. PETITION NO. 1321 - The United Illuminating Company petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed modifications to the existing East Shore Substation located at 1 Waterfront Street, New Haven, Connecticut. Decision.

  6. PETITION NO. 1323 - Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt AC and two 1.0 Megawatt AC solar photovoltaic electric generating facilities on an approximate 43 acre parcel located at 134 Bilton Road, Somers, Connecticut. Set Date for Decision.

  7. PETITION NO. 1325 - The Connecticut Light and Power Company d/b/a Eversource Energy petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for proposed modifications to an existing telecommunications facility on electric transmission line structure No. 9950, owned by Eversource Energy within an existing Eversource Energy electric transmission line right-of-way, located at the Birchwood Condominium Complex, 27 Crows Nest Lane, Danbury, Connecticut. Request for Party/Intervenor Request. Birchwood Condominium Association Objection to Petition for Declaratory Ruling. Set Date for Decision.

  8. PETITION NO. 1326 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed installation of a wireless telecommunications facility on the roof of an existing commercial building located at 1385 Post Road East, Westport, Connecticut. Request for Party/Intervenor Status. Set Date for Decision.

  9. PETITION NO. 1327 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for proposed modifications to an existing telecommunications facility located at 623 Pine Street, Bridgeport, Connecticut. Decision.

  10. Connecticut Siting Council Revised Fiscal Year 2019 Proposed Budget.

  11. Administrative Matters.

Regular Items.

Upcoming Calendar Events:

  • Petition No. 1312, Tuesday, October 31, 2017, evidentiary hearing session beginning at 11:00 a.m. in Hearing Room One, Ten Franklin Square, New Britain, Connecticut.
  • Petition No. 1313, Thursday, November 2, 2017, evidentiary hearing session beginning at 11:00 a.m. in Hearing Room One, Ten Franklin Square, New Britain, Connecticut.
  • Energy/Telecommunications meeting, Thursday, November 9, 2017, beginning at 1:00 p.m. in Hearing Room Two, Ten Franklin Square, New Britain, Connecticut.
  • Petition No. 1312, Tuesday, November 14, 2017, evidentiary hearing session beginning at 11:00 a.m. in Hearing Room One, Ten Franklin Square, New Britain, Connecticut.
  • Docket No. 476, Thursday, November 16, 2017, public hearing beginning with a 2:00 p.m. public field review, a 3:00 p.m. evidentiary hearing session, and a 6:30 p.m. public comment session at the Somers Town Hall Auditorium, 600 Main Street, Somers, Connecticut.
  • Petition No. 1313, Tuesday, November 28, 2017, evidentiary hearing session beginning at 11:00 a.m. in Hearing Room One, Ten Franklin Square, New Britain, Connecticut.
  • Petition No. 1312, Thursday, November 30, 2017, evidentiary hearing session beginning at 11:00 a.m. in Hearing Room One, Ten Franklin Square, New Britain, Connecticut.

Location: New Britain