NOTICE TO USERS The Connecticut Siting Council posts filed documents to this site as a public service.The Council disclaims any liability for the content of submissions made by parties, intervenors, public officials, and the general public. Further, while the Council seeks to be complete in its postings, the Council urges users of this site to confirm with the submitter the completeness of the postings made. The posting of any document does not constitute or imply endorsement by the Connecticut Siting Council. Finally, the Connecticut Siting Council assumes no responsibility for the use of documents posted on this site. For further information about the proper use of material posted on this site, please see the State of Connecticut disclaimer.
|
Printable Version
Note to users: The table below is an incomplete list of electric generating facilities that have been approved or denied by the Council since 1997.
Location
| Location |
Council ID |
Company |
Megawatt Capacity to the Grid |
Decision |
Project Status |
| Manchester |
Petition 360 |
Minnesota Methane LLC |
1.63 |
approved
09/30/1996 |
|
| Windsor Locks |
Petition 376 |
Hamilton Standard |
.2 |
approved
06/30/1977 |
|
| Bridgeport |
Petition 377 |
Bridgeport Energy |
520 |
approved 08/06/1997 |
Operating since 8/1/98 |
|
Middletown |
Petition 378 |
Aetna Life
Insurance Co. |
0 |
approved
07/16/1997
12/19/2000
03/13/2007 |
|
| Windsor |
Petition 378 |
Aetna Life
Insurance Co. |
0 |
approved
07/16/1997
12/19/2000
03/13/2007 |
|
| Hartford |
Petition 401 |
Hartford Steam Co. |
0 |
approved
09/24/1998 |
|
| Pomfret |
Petition 410 |
Hull Forest Products |
0 |
approved
03/24/1999 |
|
| Hartford |
Petition 427 |
Aetna Life
Insurance Co. |
0 |
approved
08/31/1999 |
|
| Wallingford |
Petition 451 |
Wallingford Energy |
250
5 units at 50 MW |
approved 06/20/00 |
Operating since 7/31/01 |
| Middletown |
Petition 482 |
HEC, Inc. |
0 |
approved
09/19/2000 |
|
| Hartford |
Petition 546 |
Pratt & Whitney |
0 |
approved 03/07/2002 |
|
| So. Windsor |
Petition 553 |
Town of So. Windsor |
0 |
approved
04/03/2002 |
|
| Norwalk |
Petition 562 |
CMEEC |
2 |
approved
06/03/2002 |
|
| Torrington |
Petition 563 |
The Torrington Co. |
0 |
approved 10/23/2002 |
|
| New Haven |
Petition 598 |
Yale University |
0 |
approved
12/19/2002 |
|
| Stamford |
|
Waterside Power LLC |
69.2 |
approved
05/06/2003
03/04/2004
07/27/2006 |
|
| Hartford |
Petition 619E |
Select Energy |
0 |
approved 05/06/2003 |
|
| Norwalk |
Petition 620E |
CMEEC |
23 |
approved 05/20/2003 |
|
| Mansfield |
Petition 639 |
UCONN |
0 |
approved 09/23/2003 |
|
| New Haven |
Petition 647 |
Nxegen, Inc. |
0 |
approved
10/14/2003 |
|
| So. Norwalk |
Petition 662 |
SNEW |
22.8 |
approved 03/04/2004 |
|
| Norwalk |
Petition 663 |
SNEW |
51 |
approved
10/07/2004 |
|
| Haddam |
Petition 671 |
CL&P |
0 |
approved
05/19/2004 |
|
| Wallingford |
Petition 672 |
CMEEC |
8 |
approved
05/19/2004 |
|
| Norwalk |
Petition 676 |
3rd Taxing District of Norwalk |
6 |
approved
06/23/2004 |
|
| Fairfield |
Petition 696 |
Johnson Controls, Inc. |
0 |
approved
10/26/2004 |
|
| Rocky Hill |
Petition 698 |
DPW |
0 |
approved
12/01/2004 |
|
| Bloomfield |
Petition 711 |
PPL |
0 |
approved
05/11/2005 |
|
| Middletown |
Petition 715 |
CL&P |
0 |
approved
07/20/2005 |
|
| Norwalk |
Petition 716 |
CL&P |
0 |
approved
07/20/2005 |
|
| Montville |
Petition 717 |
CL&P |
0 |
approved
07/20/2005 |
|
| Milford |
Petition 718 |
CL&P |
0 |
approved
07/20/2005 |
|
| Hartford |
Petition 719 |
CL&P |
0 |
approved
06/08/2005 |
|
| Norwich |
Petition 746 |
CMEEC |
2 |
approved
11/17/2005 |
|
| Wallingford |
Petition 747 |
CMEEC |
4 |
approved
11/17/2005 |
|
| E. Windsor |
Petition 751 |
Manchester Methane LLC |
3.2 |
approved 02/22/2006
modified
07/27/2006
|
|
| Wallingford |
Petition 778 |
CMEEC |
84 |
approved
09/28/2006 |
|
| Plainfield |
Petition 784 |
Plainfield Renewable Energy LLC |
37.5 |
approved 05/22/2007 |
Under construction Fall 2011 |
| Bridgeport |
Petition 785 |
Bridgeport Fuel Cell Park LLC |
14.4 |
approved
10/31/2006 |
|
| Middletown |
Petition 810 |
City of Middletown |
0 |
approved
06/07/2007 |
|
| Greenwich |
Petition 812 |
CT Jet Power LLC |
40 |
approved 07/26/2007 |
|
| New Milford |
Petition 813 |
Kimberly Clark Corp. |
17 |
approved 06/07/2007 |
|
| Wallingford |
Petition 817 |
CMEEC |
2 |
approved 07/03/2007 |
|
| Killingly |
Docket 189 |
Lake Road Generating |
792 |
approved 12/07/98 |
Operating since 5/1/02 |
| Milford |
Docket 187 |
Milford Power Co. |
544 |
approved 01/08/99 |
Operating since 5/3/04 |
| Meriden |
Docket 190 |
NRG Northeast
Generating |
544 |
approved 04/27/99
Certificate Expires 12/31/11 |
Construction Incomplete |
| Southington |
Docket 191 |
AES Southington |
(720) |
denied 05/25/99 |
n/a |
| Oxford |
Docket 192 |
Calpine |
512 |
approved 06/23/99
Certificate Expires 01/24/07 |
Construction Incomplete |
| New Milford |
Docket 193 |
Sempra Energy |
(500) |
denied 12/15/99 |
n/a |
| Middletown |
Docket 225 |
Kleen Energy Systems |
620 |
approved 3/25/03 |
Operating since 07/12/11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Approved Capacity |
3,782 MW |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Dates of operation obtained from "NEPOOL 2004-2013 Forecast Report of Capacity, Energy, Loads, and Transmission (2004 CELT Report)."
Content Last Modified on 2/1/2012 11:39:11 AM
|