CSC: Pending Matters
Common Elements

Pending Matters

 
The hyperlinks that appear below lead to web pages devoted to record materials relating to matters that are pending before the Siting Council.
 

Please note, the Connecticut Siting Council (Council) is not required to maintain an online data base of Pending Matters.  Due to a high volume of filings, the Council may not be able to keep the information found on these sites up to date.  For complete Pending Matter information, please contact the Council's staff or feel free to view the hard copy of the pertinent file in the Council’s office.  The Council endeavors to keep information up to date for the convenience of the public.

 
The Council's preferred method of service to participants in a matter is via electronic mail.  If a participant prefers to receive hard copies of documents via regular mail, please notify the Council in writing.

If you do not find the matter you are looking for, it is likely that a decision was recently rendered and the matter may be accessed through the Decisions page at the following link Council Decisions.
_____________________________________

DOCKETS
 _____________________________________

 

_____________________________________

PETITIONS
_____________________________________

PETITION NO. 1347 -  GRE GACRUX LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 16.78-megawatt AC solar photovoltaic electric generating facility located at 117 Oil Mill Road and associated electrical interconnection to Eversource Energy’s existing substation at 325 Waterford Parkway North in Waterford, Connecticut.  Request for Reconsideration.
 
PETITION NO. 1352 - Nutmeg Solar, LLC, petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 19.6-megawatt AC solar photovoltaic electric generating facility on approximately 162 acres comprised of 9 separate parcels located generally south of Bailey Road and east of Route 191 (Broad Brook Road), and associated electrical interconnection to Eversource Energy’s Scitico Substation at 20 Bailey Road in Enfield, Connecticut.
 
PETITION NO. 1354 – Chatfield Solar Fund, LLC, petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 1.98-megawatt AC solar photovoltaic electric generating facility on approximately 25 acres located generally south of Route 80 (North Branford Road) and east of Chestnut Hill Road in Killingworth, Connecticut, and associated electrical interconnection to Eversource Energy’s Green Hill Substation located at 775 Green Hill Road, Madison, Connecticut.
 
PETITION NO. 1357 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed modifications to an existing wireless telecommunications facility located at 1052 Boston Post Road, Milford, Connecticut.

PETITION NO. 1358 - Cellco Partnership d/b/a Verizon Wireless petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed installation of a small cell wireless telecommunications facility on a new approximately 34-foot Eversource-owned utility pole that is not used principally for electric distribution service located in a public right of way adjacent to 53 Goodwives River Road, Darien, Connecticut.


TOWER SHARE REQUESTS
______________________________________
  

TS-T-MOBILE-055-181031 - T-Mobile request for an order to approve tower sharing at an existing telecommunications facility located at 442 North Street, Goshen, Connecticut. Incomplete Letter

TS-T-MOBILE-042-181105 - T-Mobile Northeast LLC request for an order to approve tower sharing at an existing telecommunications facility located at 151 Young Street, East Hampton, Connecticut. Incomplete Letter

TS-DISH-166-181126 Gamma Purchasing L.L.C. (Dish) request for an order to approve tower sharing at an existing telecommunications facility located at 1233 Wolcott Road, Wolcott, Connecticut.

 

 

PETITION NO. 1133 - SUB PETITION FILINGS
 
 
 

 
The following have been acted upon by the Siting Council and await approval of their Development and Management Plans:
______________________________________


DOCKET NO. 461A - Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a 115-kilovolt (kV) bulk substation located at 290 Railroad Avenue, Greenwich, Connecticut, and two 115-kV transmission circuits extending approximately 2.3 miles between the proposed substation and the existing Cos Cob Substation, Greenwich, Connecticut, and related substation improvements. Reopening of this docket based on changed conditions pursuant to Connecticut General Statutes §4-181a(b).

DOCKET NO. 471 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located at Hamden Tax Assessor’s Map 2826, Block 24, 208 Kirk Road (a/k/a 1075 Paradise Avenue), Hamden, Connecticut.


 

DOCKET NO. 474 - The Connecticut Light & Power Company d/b/a Eversource Energy application for a Certificate of Environmental Compatibility and Public Need for the Greater Hartford-Central Connecticut Reliability Project that traverses the municipalities of Hartford, West Hartford, and Newington, which consists of (a) construction, maintenance and operation of a new 115-kilovolt (kV) electric transmission line within existing Eversource, Amtrak and public road rights-of-way and associated facilities extending overhead approximately 2.4 miles and underground approximately 1.3 miles between Eversource’s existing Newington Substation in the Town of Newington and existing Southwest Hartford Substation in the City of Hartford; (b) modifications to a .01 mile section within existing Eversource right-of-way of the existing overhead 115-kV electric transmission line connection to the Newington Substation (Newington Tap); and (c) related modifications to Newington Substation and Southwest Hartford Substation.
 

DOCKET NO. 477 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located at 46 Cemetery Road, Canterbury, Connecticut.
 
DOCKET NO. 478 - Eco-Site, Inc. and T-Mobile Northeast, LLC application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located at 63 Woodland Street, Glastonbury, Connecticut.

DOCKET NO. 481 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility located at 667, 665, 663 and 663R Main Street, Cromwell, Connecticut.

DOCKET NO. 482 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility on town-owned property behind Lyman Memorial High School located at 917 Exeter Road, Lebanon, Connecticut.

DOCKET NO. 483 - The United Illuminating Company application for a Certificate of Environmental Compatibility and Public Need for the Pequonnock Substation Rebuild Project that entails construction, maintenance, and operation of a 115/13.8-kilovolt (kV) gas insulated replacement substation facility located 700 feet southwest of UI’s existing Pequonnock substation on an approximately 3.7 acre parcel owned by PSEG Power Connecticut, LLC at 1 Kiefer Street, Bridgeport, Connecticut, and related transmission structure and interconnection improvements.

DOCKET NO. 484 - Cellco Partnership d/b/a Verizon Wireless application for a Certificate of Environmental Compatibility and Public Need for the construction, maintenance, and operation of a telecommunications facility at one of three locations at 72 Ragged Hill Road, Pomfret, Connecticut.

PETITION NO. 1184 - Beacon Falls Energy Park, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, operation, and maintenance of a 63.3 Megawatt AC fuel cell facility located on Lopus Road, Beacon Falls, Connecticut. 

PETITION NO. 1195 - SolarCity Corporation petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction and operation of a 4.05 Megawatt Community Shared Solar Photovoltaic Electric Generating facility located on municipally-owned property at 1240 Poquonnock Road, Groton, Connecticut. 

PETITION NO. 1220 -Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt and one 1.0 Megawatt Solar Photovoltaic Electric Generating facilities located at 1219 and 1240 Voluntown Road, Griswold, Connecticut.

PETITION NO. 1222 - Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt and four 1.0 Megawatt Solar Photovoltaic Electric Generating facilities located southeast of Hartford Turnpike and south of Fisk Road, Hampton, Connecticut.

PETITION NO. 1312 - Candlewood Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of a 20 megawatt AC (26.5 megawatt DC) solar photovoltaic electric generating facility located on a 163 acre parcel at 197 Candlewood Mountain Road and associated electrical interconnection to Eversource Energy’s Rocky River Substation on Kent Road in New Milford, Connecticut.

PETITION NO. 1313 – DWW Solar II, LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of a 26.4 megawatt AC solar photovoltaic electric generating facility on approximately 289 acres comprised of 5 separate and abutting privately-owned parcels located generally west of Hopmeadow Street (US 202/CT 10), north and south of Hoskins Road, and north and east of  County Road and associated electrical interconnection to Eversource Energy’s North Simsbury Substation west of Hopmeadow Street in Simsbury, Connecticut.

PETITION NO. 1328  – Windham Solar LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of one 1-megawatt (MW) and one .99-MW solar photovoltaic electric generating facilities located at 481 Mashamoquet Road, Pomfret, Connecticut.

PETITION NO. 1339 – Wallingford Renewable Energy LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 19.99 MW AC ground-mounted solar photovoltaic electric generating facility located on approximately 158 acres of 3 contiguous parcels consisting of the former Wallingford Landfill and 2 parcels owned by the Materials Innovation and Recycling Authority west of Pent Road and associated electrical interconnection to Wallingford Electric Division’s Wallingford Substation in Wallingford, 

PETITION NO. 1342 – GRE GACRUX LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 4.98-megawatt AC solar photovoltaic electric generating facility located at 232 Rimmon Road and 700 Middletown Avenue, North Haven, Connecticut.

PETITION NO. 1345 – Pawcatuck Solar Center LLC petition for a declaratory ruling, pursuant to Connecticut General Statutes §4-176 and §16-50k, for the proposed construction, maintenance and operation of a 15 MW AC solar photovoltaic electric generating facility on approximately 353 acres comprised of four abutting parcels located east of Pendleton Hill Road, north of the Pawcatuck River and south of Interstate-95 with proposed access from Ella Wheeler Road, and associated electrical interconnection to Eversource Energy’s Shunock Substation west of Pendleton Hill Road in North Stonington, Connecticut.


OTHER CSC PROCEEDINGS