CSC: PE 1227 Eversource Energy, Middlefield
PetitionNos1220_1229

PETITION NO. 1227 – Eversource Energy petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed replacement of electric transmission line structures within approximately .8 miles of existing right of way along its existing No. 1975 115-kV transmission line traversing the municipalities of Middlefield, Durham and Middletown, Connecticut, and related transmission line structure improvements.
 
 
CORRESPONDENCE
 
 
DECISION
 
 
DEVELOPMENT & MANAGEMENT PLAN
 


Content Last Modified on 6/28/2017 9:24:16 AM