CSC: PE1220_WindhamSolar_Griswold
PetitionNos1220_1229

PETITION NO. 1220 - Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt and one 1.0 Megawatt Solar Photovoltaic Electric Generating facilities located at 1219 and 1240 Voluntown Road, Griswold, Connecticut.

 

PETITION FILING

 

PROCEDURAL CORRESPONDENCE

Interrogatories to Petitioner Set 1 with Wetlands Report

Field Review 04/12/16

Responses to Set 1 Interrogatories

Mario J. Tristany, Jr., Town Planner, Town of Griswold, Letter, 04/21/16

Interrogatories to Petitioner Set 2

Responses to Set Two Interrogatories

Set Date for Decision Letter, 05/13/16

Interrogatories to Petitioner Set 3

Responses to Set Three Interrogatories, 06/10/16

 

PETITION DECISION

 Staff Report and Decision Letter 06/24/16



Content Last Modified on 6/28/2016 8:43:05 AM