PETITION NO. 1220 - Windham Solar LLC petition for a declaratory ruling that no Certificate of Environmental Compatibility and Public Need is required for the proposed construction, maintenance and operation of three 2.0 Megawatt and one 1.0 Megawatt Solar Photovoltaic Electric Generating facilities located at 1219 and 1240 Voluntown Road, Griswold, Connecticut.

 

PETITION FILING

 

PROCEDURAL CORRESPONDENCE

Interrogatories to Petitioner Set 1 with Wetlands Report

Field Review 04/12/16

Responses to Set 1 Interrogatories

Mario J. Tristany, Jr., Town Planner, Town of Griswold, Letter, 04/21/16

Interrogatories to Petitioner Set 2

Responses to Set Two Interrogatories

Set Date for Decision Letter, 05/13/16

Interrogatories to Petitioner Set 3

Responses to Set Three Interrogatories, 06/10/16

Department of Energy and Environmental Protection Correspondence, 8/28/18


PETITION DECISION

Staff Report and Decision Letter 06/24/16

 

 

DEVELOPMENT AND MANAGEMENT PLAN (D&M Plan)

Request for Site Clearing, 07/19/18

Council Site Clearing D&M Plan Interrogatories, 07/20/18

Site Clearing D&M Plan Interrogatory Responses, 07/25/18

Site Clearing D&M Plan Additional Interrogatory Responses, 8/1/18

Site Clearing D&M Plan Interrogatories, Set Two, 08/03/18

Responses to Interrogatories, Set Two, 08/17/18

Response to Interrogatory #7, 08/17/18

Council Decision on Partial D&M Plan -  Site Clearing, 08/31/18